SCHEDULED INSPECTIONS: MONDAY THRU FRIDAY
- ITEMS NEEDED FOR PERMIT:
- COPIES OF ZONING, SANITATION, DRIVEWAY AND ANY OTHER PERMITS THAT ARE REQUIRED BY THE COUNTY AND OR TOWNSHIPS.
- ONE COPY OF BUILDING PLANS; [floor plan, elevations, & cross wall section] Wall bracing details (Wall-bracing compliance worksheet can be obtained at: dsps.wi.gov Tall wall design plan for walls over 12 ft., Slab foundation & pier plan for manufactured homes. PDF files are preferred.
- RESH CHECK [heat loss calculation] WITH CHECK LIST [not needed if heating with solid fuel source only or if project is an addition less than 50% of existing structure].
- COMPLETED PERMIT APPLICATION
- erosion control plan [use plot plan and show streams, slopes, roads & dirt piles; draw in erosion control devices, silt fences.straw bales, etc
- PERMIT FEE [checks are made out to: Langlade UDC Inspections
- CONSTRUCTION DEPOSIT AGREEMENT
Begin construction after plans are approved and building permit is issue.
Inspection Schedule: Call for inspections of each construction phase after
the work is completed. Inspections will be scheduled within 2 business days of notification.
-
- FOUNDATION, TAR, TILE, and INSULATION AND ELECTRICAL METER: inspected prior to back filling
GROUND PLUMBING: pressure test is required, before basement &garage floor is poured.
2.ROUGH INSPECTION [before installation of insulation]
- General construction
- Electrical
- Meter [If not done during foundation inspection]
- Interior wiring
- Rough Plumbing: pressure test is required on above ground plumbing
- Rough heating, ventilating and air conditioning
- INSULATION (before sheet- rocking]
- FINAL 5 days notice. important: Final inspection is required before occupancy. $1000.00 a day fine assessed for unauthorized occupancy
$65.00 assessed for re-inspections